District of Columbia mechanics lien rules
D.C. Code tit. 40, ch. 3 · private projects · summarized November 2026
Preliminary noticeNot required
Notice of intentNot required
File the lien: prime contractor90 days after project completion
File the lien: sub / supplier90 days after project completion
WhereRecorder of Deeds
Serve the ownerSend a copy by certified mail to the owner within 5 business days (§ 40-301.02).
Enforce180 days after filing
ResidentialHome-improvement payment defense (§ 47-2883.03).
Public projects (bond claims)
Serve the bond claimWithin 90 days of last furnishing.
Sue on the bondWithin 1 year of last furnishing.
Bond claim service $149 + certified mail. Need a lawyer? District of Columbia construction attorneys
Let MyPlanBay handle it. Deadline tracking $15/job · preliminary notice $29 · lien e-filed $199 · release $49. Protect a job
Sources: ezel.ai 51-jurisdiction lien survey, Siteline 50-state lien chart. Laws change; confirm the details with a construction attorney licensed in District of Columbia. All states