| State | Preliminary notice | File the lien (prime) | File the lien (sub/supplier) | Enforce |
|---|---|---|---|---|
| Alabama | Subs/suppliers | 6 months after your last furnishing | 4 months after your last furnishing | 6 months after filing |
| Alaska | Subs/suppliers | 120 days after project completion | 120 days after project completion | 6 months after filing |
| Arizona | Subs/suppliers, 20 days | 120 days after project completion | 120 days after project completion | 6 months after filing |
| Arkansas | Subs/suppliers, 75 days · prime too | 120 days after your last furnishing | 120 days after your last furnishing | 15 months after filing |
| California | Subs/suppliers, 20 days | 90 days after project completion | 90 days after project completion | 90 days after filing |
| Colorado | No | 4 months after your last furnishing | 4 months after your last furnishing | 6 months after your last furnishing |
| Connecticut | Subs/suppliers, 90 days | 90 days after your last furnishing | 90 days after your last furnishing | 1 year after filing |
| Delaware | No | 180 days after project completion | 120 days after your last furnishing | With the filing |
| District of Columbia | No | 90 days after project completion | 90 days after project completion | 180 days after filing |
| Florida | Subs/suppliers, 45 days | 90 days after your last furnishing | 90 days after your last furnishing | 1 year after filing |
| Georgia | Subs/suppliers, 30 days | 90 days after your last furnishing | 90 days after your last furnishing | 365 days after filing |
| Hawaii | No | 45 days after project completion | 45 days after project completion | 3 months after filing |
| Idaho | No · prime too | 90 days after your last furnishing | 90 days after your last furnishing | 6 months after filing |
| Illinois | Subs/suppliers, 60 days | 4 months after project completion | 4 months after your last furnishing | 2 years after project completion |
| Indiana | No | 90 days after your last furnishing | 90 days after your last furnishing | 1 year after filing |
| Iowa | Subs/suppliers, 30 days | 90 days after your last furnishing | 90 days after your last furnishing | 2 years after filing |
| Kansas | No | 4 months after your last furnishing | 3 months after your last furnishing | 1 year after filing |
| Kentucky | Subs/suppliers, 120 days | 6 months after your last furnishing | 6 months after your last furnishing | 12 months after filing |
| Louisiana | No · prime too | 60 days after project completion | 60 days after project completion | 1 year after filing |
| Maine | No | — | 90 days after your last furnishing | 120 days after your last furnishing |
| Maryland | No | 180 days after your last furnishing | 180 days after your last furnishing | 1 year after filing |
| Massachusetts | Subs/suppliers, 30 days | 90 days after your last furnishing | 90 days after your last furnishing | 90 days after filing |
| Michigan | Subs/suppliers, 20 days | 90 days after your last furnishing | 90 days after your last furnishing | 1 year after filing |
| Minnesota | Subs/suppliers, 45 days · prime too | 120 days after your last furnishing | 120 days after your last furnishing | 1 year after your last furnishing |
| Mississippi | Subs/suppliers, 30 days | 90 days after your last furnishing | 90 days after your last furnishing | 180 days after filing |
| Missouri | No · prime too | 6 months after your last furnishing | 6 months after your last furnishing | 6 months after filing |
| Montana | Subs/suppliers, 20 days | 90 days after your last furnishing | 90 days after your last furnishing | 2 years after filing |
| Nebraska | No | 120 days after your last furnishing | 120 days after your last furnishing | 2 years after filing |
| Nevada | Subs/suppliers, 31 days | 90 days after your last furnishing | 90 days after your last furnishing | 6 months after filing |
| New Hampshire | Subs/suppliers | — | — | 120 days after your last furnishing |
| New Jersey | No | 90 days after your last furnishing | 90 days after your last furnishing | 1 year after your last furnishing |
| New Mexico | Subs/suppliers, 60 days | 120 days after project completion | 90 days after project completion | 2 years after filing |
| New York | No | 8 months after your last furnishing | 8 months after your last furnishing | 1 year after filing |
| North Carolina | All, 15 days | 120 days after your last furnishing | 120 days after your last furnishing | 180 days after your last furnishing |
| North Dakota | No | 90 days after your last furnishing | 90 days after your last furnishing | 3 years after filing |
| Ohio | Subs/suppliers, 21 days | 75 days after your last furnishing | 75 days after your last furnishing | 6 years after filing |
| Oklahoma | Subs/suppliers, 75 days | 4 months after your last furnishing | 90 days after your last furnishing | 1 year after filing |
| Oregon | Subs/suppliers, 8 days · prime too | 75 days after your last furnishing | 75 days after your last furnishing | 120 days after filing |
| Pennsylvania | Subs/suppliers, 45 days | 6 months after your last furnishing | 6 months after your last furnishing | 2 years after filing |
| Rhode Island | No · prime too | 200 days after your last furnishing | 200 days after your last furnishing | 40 days after filing |
| South Carolina | No | 90 days after your last furnishing | 90 days after your last furnishing | 6 months after your last furnishing |
| South Dakota | Subs/suppliers, 60 days | 120 days after your last furnishing | 120 days after your last furnishing | 6 years after your last furnishing |
| Tennessee | Subs/suppliers, 90 days | 90 days after project completion | 90 days after project completion | 90 days after filing |
| Texas | Subs/suppliers | 15th day of the 4th month after the month of completion | 15th day of the 4th month after the month of completion | 1 year after the last day to file |
| Utah | All, 20 days | 180 days after project completion | 180 days after project completion | 180 days after filing |
| Vermont | Subs/suppliers | 180 days after your last furnishing | 180 days after your last furnishing | 180 days after filing |
| Virginia | All, 30 days | 90 days after the end of the month you last worked | 90 days after the end of the month you last worked | 6 months after filing |
| Washington | Subs/suppliers, 60 days | 90 days after your last furnishing | 90 days after your last furnishing | 8 months after filing |
| West Virginia | No | 100 days after project completion | 100 days after your last furnishing | 6 months after filing |
| Wisconsin | Subs/suppliers, 60 days · prime too | 6 months after your last furnishing | 6 months after your last furnishing | 2 years after filing |
| Wyoming | Subs/suppliers, 30 days · prime too | 150 days after your last furnishing | 120 days after your last furnishing | 180 days after filing |
Public projects: payment bond claims
Liens can't attach to public property. Subs and suppliers claim on the prime contractor's payment bond instead. Sources: NCS bond claim and suit deadlines (50 states), NCS: What is the Miller Act.
| Jurisdiction | Serve the bond claim | Sue on the bond |
|---|---|---|
| Federal projects (Miller Act) | Second-tier subs and suppliers: written notice to the prime contractor within 90 days of last furnishing. | Sue in U.S. District Court after 90 days but within 1 year of last furnishing. |
| Alabama | Notice at least 45 days before filing suit. | Within 1 year of final settlement. |
| Alaska | Within 90 days of last furnishing. | Within 1 year of final settlement of the contract. |
| Arizona | Within 90 days of last furnishing. | Within 1 year of last furnishing. |
| Arkansas | Set by the bond's terms (often 90 days after last furnishing) | Within 6 months after final payment. |
| California | Within 75 days of completion (15 days after a recorded notice of completion). | Within 6 months after the stop-payment-notice period ends. |
| Colorado | Set by the bond's terms (often 90 days after last furnishing) | Within 6 months of project completion. |
| Connecticut | Within 180 days of last furnishing. | Within 1 year of last furnishing. |
| Delaware | Set by the bond's terms (often 90 days after last furnishing) | Within 1 year of completion (3 years of last furnishing if the bond sets no limit). |
| District of Columbia | Within 90 days of last furnishing. | Within 1 year of last furnishing. |
| Florida | Within 90 days of last furnishing. | Within 1 year of last furnishing. |
| Georgia | Within 90 days of last furnishing. | Within 1 year of completion and acceptance. |
| Hawaii | Within 90 days of last furnishing. | Within 1 year of last furnishing. |
| Idaho | Within 90 days of last furnishing. | Within 1 year of last furnishing. |
| Illinois | Within 180 days of last furnishing. | Within 1 year of last furnishing (sooner if you served a public improvement lien). |
| Indiana | Within 60 days of last furnishing. | Suit may be filed 60 days after final completion and acceptance; check the bond. |
| Iowa | Within 30 days of completion. | Within 60 days of completion and final acceptance. |
| Kansas | Set by the bond's terms (often 90 days after last furnishing) | Within 6 months of project completion. |
| Kentucky | Set by the bond's terms (often 90 days after last furnishing) | Set by the bond (often 1 year of last furnishing). |
| Louisiana | Within 45 days after acceptance or notice of default. | Within 1 year of acceptance or default notice. |
| Maine | Within 90 days of last furnishing. | Within 1 year of last furnishing. |
| Maryland | Within 90 days of last furnishing. | Within 1 year of final acceptance. |
| Massachusetts | Within 65 days of last furnishing. | Within 1 year of last furnishing. |
| Michigan | Within 90 days of last furnishing. | Within 1 year of final payment to the prime contractor. |
| Minnesota | Within 120 days of last furnishing. | Within 1 year of last furnishing. |
| Mississippi | Within 90 days of last furnishing. | Within 1 year of last furnishing. |
| Missouri | Set by the bond's terms (often 90 days after last furnishing) | Set by the bond (often 1 year of last furnishing). |
| Montana | Within 90 days of completion and acceptance. | Set by the bond (often 1 year of last furnishing). |
| Nebraska | Within 4 months of last furnishing. | Within 1 year of final settlement. |
| Nevada | Within 90 days of last furnishing. | Within 1 year of last furnishing. |
| New Hampshire | Within 90 days of completion and acceptance. | Within 1 year of filing the statement of claim. |
| New Jersey | Within 1 year less 90 days of last furnishing. | Within 1 year of last furnishing. |
| New Mexico | Within 90 days of last furnishing. | Within 1 year of final settlement. |
| New York | Within 120 days of last furnishing. | Within 1 year of completion and acceptance. |
| North Carolina | Within 120 days of last furnishing. | Within 1 year of last furnishing or final settlement, whichever is later. |
| North Dakota | Within 90 days of last furnishing. | Within 1 year of completion and acceptance. |
| Ohio | After last furnishing and within 90 days of acceptance. | Within 1 year of acceptance. |
| Oklahoma | Within 90 days of last furnishing. | Within 1 year of last furnishing. |
| Oregon | Within 180 days of last furnishing. | Within 2 years of last furnishing. |
| Pennsylvania | Within 90 days of last furnishing. | Within 1 year of last furnishing. |
| Rhode Island | Within 90 days of last furnishing. | Within 2 years of last furnishing (or later if the bond allows). |
| South Carolina | Within 90 days of last furnishing. | Within 1 year of last furnishing. |
| South Dakota | Set by the bond's terms (often 90 days after last furnishing) | Within 1 year of completion and final settlement. |
| Tennessee | Within 90 days of project completion. | Within 6 months of last furnishing or completion. |
| Texas | By the 15th day of the 3rd month after each month you furnished and weren't paid. | Within 1 year of serving the bond claim notice. |
| Utah | Recommended within 90 days of last furnishing. | Within 1 year of last furnishing. |
| Vermont | Set by the bond's terms (often 90 days after last furnishing) | Set by the bond (often 1 year of last furnishing). |
| Virginia | Within 90 days of last furnishing. | Within 1 year of last furnishing. |
| Washington | Within 30 days of completion and acceptance. | Recommended within 4 months of completion/acceptance, or per the bond. |
| West Virginia | Set by the bond's terms (often 90 days after last furnishing) | Set by the bond (often 1 year of last furnishing). |
| Wisconsin | Recommended within 90 days of last furnishing. | Within 1 year after completion of the contract work. |
| Wyoming | Recommended within 90 days of last furnishing. | Within 1 year after first publication of notice of final payment. |