Fla. Stat. ch. 713 · private projects · summarized November 2026

Preliminary noticeNotice to Owner before or within 45 days of first furnishing (§ 713.06).
Notice of intentNot required
File the lien: prime contractor90 days after your last furnishing
File the lien: sub / supplier90 days after your last furnishing
WhereClerk of court (official records) of the county
Serve the ownerServe the owner before recording or within 15 days after (§ 713.08(4)(c)).
Enforce1 year after filing
Notice of completionA Notice of Contest shortens the time to sue to 60 days.
ResidentialPrime contractors must serve a final payment affidavit at least 5 days before suing.

Public projects (bond claims)

Serve the bond claimWithin 90 days of last furnishing.
Sue on the bondWithin 1 year of last furnishing.

Bond claim service $149 + certified mail. Need a lawyer? Florida construction attorneys

Let MyPlanBay handle it. Deadline tracking $15/job · preliminary notice $29 · lien e-filed $199 · release $49. Protect a job

Sources: ezel.ai 51-jurisdiction lien survey, Siteline 50-state lien chart. Laws change; confirm the details with a construction attorney licensed in Florida. All states