Iowa mechanics lien rules
Iowa Code ch. 572 · private projects · summarized November 2026
Preliminary noticeCommercial suppliers notify the GC within 30 days; residential subs post a notice on the state registry before the owner pays in full.
Notice of intentNot required
File the lien: prime contractor90 days after your last furnishing
File the lien: sub / supplier90 days after your last furnishing
WhereIowa Mechanics' Notice and Lien Registry (online)
Serve the ownerThe registry mails the owner automatically (§ 572.8(2)).
Enforce2 years after filing
ResidentialResidential GC posts a notice of commencement within 10 days; skipped residential notices bar the lien.
Public projects (bond claims)
Serve the bond claimWithin 30 days of completion.
Sue on the bondWithin 60 days of completion and final acceptance.
Bond claim service $149 + certified mail. Need a lawyer? Iowa construction attorneys
Let MyPlanBay handle it. Deadline tracking $15/job · preliminary notice $29 · lien e-filed $199 · release $49. Protect a job
Sources: ezel.ai 51-jurisdiction lien survey, Siteline 50-state lien chart. Laws change; confirm the details with a construction attorney licensed in Iowa. All states