Louisiana mechanics lien rules

La. R.S. 9:4801 et seq. · private projects · summarized November 2026

Preliminary noticeNot required
Contracts over $100,000: file a notice of contract before work begins (§ 9:4811).
Notice of intentNot required
File the lien: prime contractor60 days after project completion
File the lien: sub / supplier60 days after project completion
WhereClerk of court (mortgage records) of the parish
Serve the ownerCopy to the owner within the filing period if an address is listed (§ 9:4822(B)).
Enforce1 year after filing
Notice of completionA filed notice of termination starts a 30-day clock.
ResidentialResidential: Truth in Construction Act notice.

Public projects (bond claims)

Serve the bond claimWithin 45 days after acceptance or notice of default.
Sue on the bondWithin 1 year of acceptance or default notice.

Bond claim service $149 + certified mail. Need a lawyer? Louisiana construction attorneys

Let MyPlanBay handle it. Deadline tracking $15/job · preliminary notice $29 · lien e-filed $199 · release $49. Protect a job

Sources: ezel.ai 51-jurisdiction lien survey, Siteline 50-state lien chart. Laws change; confirm the details with a construction attorney licensed in Louisiana. All states