Massachusetts mechanics lien rules
M.G.L. c. 254 · private projects · summarized November 2026
Preliminary noticeLower-tier claimants may send an identification notice within 30 days (§ 4).
Notice of intentNot required
File the lien: prime contractor90 days after your last furnishing
File the lien: sub / supplier90 days after your last furnishing
WhereRegistry of deeds (notice of contract, then statement of account)
Serve the ownerRecord an attested copy of the complaint within 30 days after suing.
Enforce90 days after filing
Notice of completionNotice of substantial completion starts a 60-day clock; termination notice 90 days.
Public projects (bond claims)
Serve the bond claimWithin 65 days of last furnishing.
Sue on the bondWithin 1 year of last furnishing.
Bond claim service $149 + certified mail. Need a lawyer? Massachusetts construction attorneys
Let MyPlanBay handle it. Deadline tracking $15/job · preliminary notice $29 · lien e-filed $199 · release $49. Protect a job
Sources: ezel.ai 51-jurisdiction lien survey, Siteline 50-state lien chart. Laws change; confirm the details with a construction attorney licensed in Massachusetts. All states