Montana mechanics lien rules

MCA §§ 71-3-521 to -564 · private projects · summarized November 2026

Preliminary noticeNotice of right to claim a lien within 20 days of first furnishing (45 days on lender-funded jobs) (§ 71-3-531).
Notice of intentNot required
File the lien: prime contractor90 days after your last furnishing
File the lien: sub / supplier90 days after your last furnishing
WhereCounty clerk and recorder
Serve the ownerServe the owner before filing (§ 71-3-534).
Enforce2 years after filing
ResidentialOwner-occupied homes always use 20 days.

Public projects (bond claims)

Serve the bond claimWithin 90 days of completion and acceptance.
Sue on the bondSet by the bond (often 1 year of last furnishing).

Bond claim service $149 + certified mail. Need a lawyer? Montana construction attorneys

Let MyPlanBay handle it. Deadline tracking $15/job · preliminary notice $29 · lien e-filed $199 · release $49. Protect a job

Sources: ezel.ai 51-jurisdiction lien survey, Siteline 50-state lien chart. Laws change; confirm the details with a construction attorney licensed in Montana. All states