Utah mechanics lien rules

Utah Code tit. 38, ch. 1a · private projects · summarized November 2026

Preliminary noticePreliminary notice on the State Construction Registry within 20 days of first furnishing (§ 38-1a-501).
Notice of intentNot required
File the lien: prime contractor180 days after project completion
File the lien: sub / supplier180 days after project completion
WhereCounty recorder
Serve the ownerSend a copy to the owner within 30 days (§ 38-1a-502(4)).
Enforce180 days after filing
Notice of completionA filed notice of completion cuts filing to 90 days.
ResidentialPaid-in-full defense for owner-occupied homes.

Public projects (bond claims)

Serve the bond claimRecommended within 90 days of last furnishing.
Sue on the bondWithin 1 year of last furnishing.

Bond claim service $149 + certified mail. Need a lawyer? Utah construction attorneys

Let MyPlanBay handle it. Deadline tracking $15/job · preliminary notice $29 · lien e-filed $199 · release $49. Protect a job

Sources: ezel.ai 51-jurisdiction lien survey, Siteline 50-state lien chart. Laws change; confirm the details with a construction attorney licensed in Utah. All states

Share

EmailWhatsAppLinkedInFacebook