Virginia mechanics lien rules

Va. Code §§ 43-1 to -23.2 · private projects · summarized November 2026

Preliminary notice1-2 family dwellings with a named lien agent: notify the agent within 30 days of first work (§ 43-4.01(C)).
Notice of intentNot required
File the lien: prime contractor90 days after the end of the month you last worked
File the lien: sub / supplier90 days after the end of the month you last worked
WhereClerk of the circuit court
Serve the ownerPrime contractors file an owner-mailing certification; subs notify the owner (§§ 43-4, 43-7).
Enforce6 months after filing
ResidentialMust also be within 90 days of completion; amounts more than 150 days old are generally excluded.

Public projects (bond claims)

Serve the bond claimWithin 90 days of last furnishing.
Sue on the bondWithin 1 year of last furnishing.

Bond claim service $149 + certified mail. Need a lawyer? Virginia construction attorneys

Let MyPlanBay handle it. Deadline tracking $15/job · preliminary notice $29 · lien e-filed $199 · release $49. Protect a job

Sources: ezel.ai 51-jurisdiction lien survey, Siteline 50-state lien chart. Laws change; confirm the details with a construction attorney licensed in Virginia. All states