Wisconsin mechanics lien rules
Wis. Stat. §§ 779.01-.17 · private projects · summarized November 2026
Preliminary noticeDownstream claimants serve notice within 60 days of first furnishing (§ 779.02).
Prime contractors put the notice in the owner contract, or serve it within 10 days (§ 779.02).
Prime contractors put the notice in the owner contract, or serve it within 10 days (§ 779.02).
Notice of intent30-day notice of intent to file before filing (§ 779.06(2)).
File the lien: prime contractor6 months after your last furnishing
File the lien: sub / supplier6 months after your last furnishing
WhereClerk of circuit court
Serve the ownerServe a copy on the owner within 30 days of filing.
Enforce2 years after filing
Public projects (bond claims)
Serve the bond claimRecommended within 90 days of last furnishing.
Sue on the bondWithin 1 year after completion of the contract work.
Bond claim service $149 + certified mail. Need a lawyer? Wisconsin construction attorneys
Let MyPlanBay handle it. Deadline tracking $15/job · preliminary notice $29 · lien e-filed $199 · release $49. Protect a job
Sources: ezel.ai 51-jurisdiction lien survey, Siteline 50-state lien chart. Laws change; confirm the details with a construction attorney licensed in Wisconsin. All states