Wyoming mechanics lien rules

W.S. §§ 29-2-101 to -112 · private projects · summarized November 2026

Preliminary noticeNotice of right to lien within 30 days of first furnishing (§ 29-2-112(a)).
Contractors give the notice before receiving the owner's first payment.
Notice of intentNotice of intent to file at least 20 days before filing (§ 29-2-107(a)).
File the lien: prime contractor150 days after your last furnishing
File the lien: sub / supplier120 days after your last furnishing
WhereCounty clerk
Serve the ownerSend notice to the record owner within 30 days of filing (§ 29-1-312(c)).
Enforce180 days after filing

Public projects (bond claims)

Serve the bond claimRecommended within 90 days of last furnishing.
Sue on the bondWithin 1 year after first publication of notice of final payment.

Bond claim service $149 + certified mail. Need a lawyer? Wyoming construction attorneys

Let MyPlanBay handle it. Deadline tracking $15/job · preliminary notice $29 · lien e-filed $199 · release $49. Protect a job

Sources: ezel.ai 51-jurisdiction lien survey, Siteline 50-state lien chart. Laws change; confirm the details with a construction attorney licensed in Wyoming. All states