Alaska mechanics lien rules
AS 34.35.050-.120 · private projects · summarized November 2026
Preliminary noticeOptional notice of right to lien (§ 34.35.064); protects you if the owner records a notice of completion.
Notice of intentNot required
File the lien: prime contractor120 days after project completion
File the lien: sub / supplier120 days after project completion
WhereRecorder's office for the recording district
Serve the ownerNo post-recording step.
Enforce6 months after filing
Notice of completionOwner's notice of completion cuts the window to 15 days for claimants without a recorded notice of right to lien.
Public projects (bond claims)
Serve the bond claimWithin 90 days of last furnishing.
Sue on the bondWithin 1 year of final settlement of the contract.
Bond claim service $149 + certified mail. Need a lawyer? Alaska construction attorneys
Let MyPlanBay handle it. Deadline tracking $15/job · preliminary notice $29 · lien e-filed $199 · release $49. Protect a job
Sources: ezel.ai 51-jurisdiction lien survey, Siteline 50-state lien chart. Laws change; confirm the details with a construction attorney licensed in Alaska. All states