Arizona mechanics lien rules
A.R.S. §§ 33-981 to -1008 · private projects · summarized November 2026
Preliminary notice20-day preliminary notice to owner, prime contractor and lender (§ 33-992.01).
Notice of intentNot required
File the lien: prime contractor120 days after project completion
File the lien: sub / supplier120 days after project completion
WhereCounty recorder / register of deeds
Serve the ownerMail a copy to the owner after recording (§ 33-993(A)).
Enforce6 months after filing
Notice of completionRecorded notice of completion cuts filing to 60 days.
ResidentialOwner-occupant: only contractors with a direct written contract can lien (§ 33-1002).
Public projects (bond claims)
Serve the bond claimWithin 90 days of last furnishing.
Sue on the bondWithin 1 year of last furnishing.
Bond claim service $149 + certified mail. Need a lawyer? Arizona construction attorneys
Let MyPlanBay handle it. Deadline tracking $15/job · preliminary notice $29 · lien e-filed $199 · release $49. Protect a job
Sources: ezel.ai 51-jurisdiction lien survey, Siteline 50-state lien chart. Laws change; confirm the details with a construction attorney licensed in Arizona. All states