Delaware mechanics lien rules
25 Del. C. ch. 27 · private projects · summarized November 2026
Preliminary noticeNot required
Notice of intentNot required
File the lien: prime contractor180 days after project completion
File the lien: sub / supplier120 days after your last furnishing
WhereSuperior Court (the statement of claim is the complaint)
Serve the ownerServed by writ of scire facias (§ 2715).
EnforceThe filing starts the case
ResidentialOwner of a sole residence who paid the contractor in full has a defense (§ 2707).
Public projects (bond claims)
Serve the bond claimSet by the bond's terms (often 90 days after last furnishing)
Sue on the bondWithin 1 year of completion (3 years of last furnishing if the bond sets no limit).
Bond claim service $149 + certified mail. Need a lawyer? Delaware construction attorneys
Let MyPlanBay handle it. Deadline tracking $15/job · preliminary notice $29 · lien e-filed $199 · release $49. Protect a job
Sources: ezel.ai 51-jurisdiction lien survey, Siteline 50-state lien chart. Laws change; confirm the details with a construction attorney licensed in Delaware. All states