Georgia mechanics lien rules

O.C.G.A. §§ 44-14-360 to -369 · private projects · summarized November 2026

Preliminary noticeNotice to Contractor within 30 days is required if a Notice of Commencement was filed (§ 44-14-361.5); otherwise optional.
Notice of intentNot required
File the lien: prime contractor90 days after your last furnishing
File the lien: sub / supplier90 days after your last furnishing
WhereClerk of superior court of the county
Serve the ownerSend a copy by registered or certified mail to the owner within 2 business days (§ 44-14-361.1).
Enforce365 days after filing
Notice of completionAn owner's Notice of Contest shortens the time to sue to 60 days (§ 44-14-368).
ResidentialSame deadlines for residential. File a notice of the lawsuit within 30 days of suing.

Public projects (bond claims)

Serve the bond claimWithin 90 days of last furnishing.
Sue on the bondWithin 1 year of completion and acceptance.

Bond claim service $149 + certified mail. Need a lawyer? Georgia construction attorneys

Let MyPlanBay handle it. Deadline tracking $15/job · preliminary notice $29 · lien e-filed $199 · release $49. Protect a job