Nebraska mechanics lien rules
Neb. Rev. Stat. §§ 52-125 to -159 · private projects · summarized November 2026
Preliminary noticeNot required
Notice of intentNot required
File the lien: prime contractor120 days after your last furnishing
File the lien: sub / supplier120 days after your last furnishing
WhereRegister of deeds
Serve the ownerProtected-party owners get a copy within 10 days after recording (§ 52-135(3)).
Enforce2 years after filing
ResidentialLien cap for protected parties (§ 52-136).
Public projects (bond claims)
Serve the bond claimWithin 4 months of last furnishing.
Sue on the bondWithin 1 year of final settlement.