Oregon mechanics lien rules
ORS 87.001-.093 · private projects · summarized November 2026
Preliminary noticeNotice of right to lien; it protects work from 8 business days before delivery (§ 87.021(1)).
Residential: give the owner the Information Notice to Owner (§ 87.093).
Residential: give the owner the Information Notice to Owner (§ 87.093).
Notice of intentNot required
File the lien: prime contractor75 days after your last furnishing
File the lien: sub / supplier75 days after your last furnishing
WhereCounty clerk (recording)
Serve the ownerMail owner and mortgagee notice of filing within 20 days (§ 87.039).
Enforce120 days after filing
ResidentialNotice of intent to foreclose 10 days before suing; written contract required over $2,000.
Public projects (bond claims)
Serve the bond claimWithin 180 days of last furnishing.
Sue on the bondWithin 2 years of last furnishing.
Bond claim service $149 + certified mail. Need a lawyer? Oregon construction attorneys
Let MyPlanBay handle it. Deadline tracking $15/job · preliminary notice $29 · lien e-filed $199 · release $49. Protect a job
Sources: ezel.ai 51-jurisdiction lien survey, Siteline 50-state lien chart. Laws change; confirm the details with a construction attorney licensed in Oregon. All states