South Carolina mechanics lien rules
S.C. Code §§ 29-5-10 to -440 · private projects · summarized November 2026
Preliminary noticeNot required
Notice of intentNot required
File the lien: prime contractor90 days after your last furnishing
File the lien: sub / supplier90 days after your last furnishing
WhereRegister of deeds
Serve the ownerServe the owner within the same 90 days (§ 29-5-90).
Enforce6 months after your last furnishing
ResidentialSubs with no contract can notify the owner of work and value (§ 29-5-40).
Public projects (bond claims)
Serve the bond claimWithin 90 days of last furnishing.
Sue on the bondWithin 1 year of last furnishing.
Bond claim service $149 + certified mail. Need a lawyer? South Carolina construction attorneys
Let MyPlanBay handle it. Deadline tracking $15/job · preliminary notice $29 · lien e-filed $199 · release $49. Protect a job
Sources: ezel.ai 51-jurisdiction lien survey, Siteline 50-state lien chart. Laws change; confirm the details with a construction attorney licensed in South Carolina. All states