South Dakota mechanics lien rules
S.D.C.L. ch. 44-9 · private projects · summarized November 2026
Preliminary noticeIf a Notice of Project Commencement was filed, notify contractor and owner within 60 days of last furnishing (§ 44-9-53).
Notice of intentNot required
File the lien: prime contractor120 days after your last furnishing
File the lien: sub / supplier120 days after your last furnishing
WhereRegister of deeds
Serve the ownerMail the statement to the owner by certified mail before filing (§ 44-9-17).
Enforce6 years after your last furnishing
Public projects (bond claims)
Serve the bond claimSet by the bond's terms (often 90 days after last furnishing)
Sue on the bondWithin 1 year of completion and final settlement.
Bond claim service $149 + certified mail. Need a lawyer? South Dakota construction attorneys
Let MyPlanBay handle it. Deadline tracking $15/job · preliminary notice $29 · lien e-filed $199 · release $49. Protect a job
Sources: ezel.ai 51-jurisdiction lien survey, Siteline 50-state lien chart. Laws change; confirm the details with a construction attorney licensed in South Dakota. All states