Washington mechanics lien rules
RCW 60.04 · private projects · summarized November 2026
Preliminary noticeNotice of right to lien protects work from 60 days before it's sent (10 days for new single-family) (RCW 60.04.031).
Notice of intentNot required
File the lien: prime contractor90 days after your last furnishing
File the lien: sub / supplier90 days after your last furnishing
WhereCounty auditor
Serve the ownerMail or serve the recorded lien on the owner within 14 days (RCW 60.04.091).
Enforce8 months after filing
Public projects (bond claims)
Serve the bond claimWithin 30 days of completion and acceptance.
Sue on the bondRecommended within 4 months of completion/acceptance, or per the bond.
Bond claim service $149 + certified mail. Need a lawyer? Washington construction attorneys