Wyoming mechanics lien rules
W.S. §§ 29-2-101 to -112 · private projects · summarized November 2026
Preliminary noticeNotice of right to lien within 30 days of first furnishing (§ 29-2-112(a)).
Contractors give the notice before receiving the owner's first payment.
Contractors give the notice before receiving the owner's first payment.
Notice of intentNotice of intent to file at least 20 days before filing (§ 29-2-107(a)).
File the lien: prime contractor150 days after your last furnishing
File the lien: sub / supplier120 days after your last furnishing
WhereCounty clerk
Serve the ownerSend notice to the record owner within 30 days of filing (§ 29-1-312(c)).
Enforce180 days after filing
Public projects (bond claims)
Serve the bond claimRecommended within 90 days of last furnishing.
Sue on the bondWithin 1 year after first publication of notice of final payment.
Bond claim service $149 + certified mail. Need a lawyer? Wyoming construction attorneys
Let MyPlanBay handle it. Deadline tracking $15/job · preliminary notice $29 · lien e-filed $199 · release $49. Protect a job
Sources: ezel.ai 51-jurisdiction lien survey, Siteline 50-state lien chart. Laws change; confirm the details with a construction attorney licensed in Wyoming. All states